End-to-End Execution

Turnkey Clean Room & Industrial HVAC Installation

Precision engineered solutions for critical environments. From heat load calculations and custom AHU fabrication to final GMP commissioning.

Turnkey Clean Room HVAC Installation
Complete Project Ownership

Single Point Responsibility

Eliminate vendor finger-pointing. AIRPACK manufactures the units, lays the ductwork, installs the controls, and validates the clean room.

Structured Process

The 6-Stage Turnkey Methodology

01Phase 01

Consultation & Heat Load

Detailed room heat load calculation, CFM requirements, ambient peak consideration, and space zoning.

02Phase 02

CFD Modeling & Blueprint

Computational Fluid Dynamics air pattern mapping, duct routing blueprints, and acoustic calculations.

03Phase 03

Precision Manufacturing

In-house casing fabrication, coil assembly, fan dynamic balancing, and pressure integrity testing in Borivali.

04Phase 04

On-Site Installation

Rigid duct erection, thermal insulation wrapping, damper synchronization, and electrical panel cabling.

05Phase 05

DOP / PAO Testing & Validation

HEPA filter integrity testing, particle count verification, airflow velocity measurement, and IQ/OQ dossier.

06Phase 06

Lifecycle Maintenance

Scheduled filter replacements, motor amperage checks, and round-the-clock emergency support across Maharashtra.